65th Street Reconstruction- Phase 1

PURPOSE

To improve the pavement conditions, replace deteriorating sidewalks, and upgrade aging underground utilities while improving operational safety for pedestrians, bicyclists, and vehicles.

The original scope of the 65th Street Reconstruction Project was 66th St/Rae Drive to Nicollet Avenue. It was determined through pavement and utility condition assessments that this project could be delayed until 2021; however, potential redevelopment (The HUB) along the segment from Grand Avenue to Nicollet Avenue will necessitate road and utility reconstruction in 2020. Therefore, the project has been divided into two smaller projects: 

  • Phase 1- Nicollet Avenue to Grand Avenue
  • Phase 2- Grand Avenue to Rae Drive/66th Street

The scope of the project also includes an examination of pedestrian crossings along Nicollet Avenue for potential improvements as part of the planned 2020 mill and overlay of the roadway by Hennepin County.

OPEN HOUSE #1- DECEMBER 12, 2018

OPEN HOUSE #2- SPRING 2019

This open house will present the layout alternatives created with the feedback received from the public at open house #1. This meeting will also provided the opportunity for the public to comment on design alternatives and provide more feedback.

OPEN HOUSE #3- SUMMER 2019

This meeting will present the preferred final layout for public comment.

PROJECT ELEMENTS

PROJECTED TIMELINE

  • Open House #1 – December 12, 2018
  • Open House #2 – Spring 2019
  • Open House #3 – Summer 2019
  • Preliminary Design- Summer 2019
  • Final Design/Council Approval- Fall 2019
  • Construction- 2020

CONTACT

Jeff Pearson
City Engineer
612-861-9791
Email