Road Work Updates

LYNDALE AVENUE RECONSTRUCTION

October 18th Lyndale Reconstruction Updates:

  • All of the water main, sanitary sewer, and storm sewer work is now complete for the project

  • Crews are currently grading from 67th to 66th St.
  • Curb and gutter will be poured up to the 66th roundabout this week as well as some sidewalk between 68th St. and 67th St.

  • The contractor is planning to pave the base layers of asphalt through 68th and up 67th St. early next week

  • Traffic on the North end of Lyndale is still detoured to Lake Shore Dr. at 66th and then to Lyndale Ave. to access 67th St. and the area businesses

  • Landscaping crews will also be laying more sod and installing more trees in the next couple of weeks as well as installing the fencing and permanent signage along the corridor

  • Thank you for your patience! The Lyndale project remains on track for substantial completion by mid-November (weather dependent)!

October 16th, 2019 Reconstruction Video Update!

Lyndale Reconstruction Podcast – That’s Rich(field) (Episode XXII)

October 9th, 2019, Lyndale Avenue Reconstruction Video Update

October 2nd, 2019, Lyndale Avenue Reconstruction Video Update

September 25th, 2019, Lyndale Avenue Reconstruction Video Update

September 18th, 2019, Lyndale Avenue Reconstruction Video Update

September 11th, 2019, Lyndale Avenue Reconstruction Video Update

September 5th, 2019, Lyndale Avenue Reconstruction Video Update

August 28th, 2019, Lyndale Reconstruction Video Update

August 22nd, 2019, Lyndale Reconstruction Video Update

August 14th, 2019, Lyndale Reconstruction Video Update

August 8th, 2019, Lyndale Reconstruction Video Update

July 31st, 2019, Lyndale Reconstruction Video Update

July 24th, 2019, Lyndale Reconstruction Video Update

July 19th, 2019, Lyndale Reconstruction Video Update

July 10th, 2019, Lyndale Reconstruction Video Update

July 2nd, 2019, Lyndale Reconstruction Video Update

June 19th, 2019, Lyndale Reconstruction Video Update

June 12th, 2019, Lyndale Reconstruction Video Update

June 6th, 2019, Lyndale Reconstruction Video Update

May 31st, 2019, Lyndale Reconstruction Video Update

May 22nd, 2019, Lyndale Reconstruction Video Update

May 16th, 2019, Lyndale Reconstruction Video Update

May 8th, 2019, Lyndale Reconstruction Video Update

May 2nd, 2019, Lyndale Reconstruction Video Update

Reconstruction Began April 29th!

Lyndale Avenue reconstruction began Monday, April 29th! Reconstruction will first take place at 76th Street and extend up to 70th Street. Expect local-traffic detours in this area. Through-traffic is asked to avoid the work zone and use the official detour via 66th Street to Nicollet to 77th Street.

Kick-Off Open House Held on April 25th!

The Lyndale Reconstruction Kick-off Open House was held at Richfield City Hall on April 25th from 4-7pm! Residents joined the project staff and contractor to discuss the Lyndale Avenue Reconstruction Project and learned about the expected project timeline and asked questions!

Ground breaking is set for the last Monday in April!

At the April 9, 2019 meeting Richfield City Council approved the final design layout for the Lyndale Avenue Project. Click here to view the Council approved preliminary design layout.

MORE INFO


66TH STREET RECONSTRUCTION PROJECT

66th St. Restoration continues through August

What to expect soon

Lane shifts and other minor traffic impacts may occur. For any properties that will experience temporary driveway access impacts, we will deliver printed notifications in advance.

Through August, Crews will be working on a number of projects, including:

  • Permanent striping
  • Sign installation
  • Landscaping (led by the City of Richfield)
  • Final site clean-up

2018 Construction Highlights

During 2018, crews reconstructed 66th Street between Humboldt and Portland avenues, including:

  • Replacing underlying soil to improve infrastructure support and drainage
  • Updating the aging underground water main, storm and sanitary sewers to reduce needs to repair and replace pipes in the near future
  • Replacing curbs and gutters and resurfacing the road to address deteriorating pavement and drainage concerns
  • Moving overhead utilities underground (work will be completed throughout this winter)

Corridor ready for all users

While the construction addressed many things you won’t be able to see or instantly appreciate, there are many benefits you will be able to enjoy every day:

  • New traffic flow improvements, including roundabouts at Nicollet and Lyndale avenues
  • New pavement providing a smoother ride when traveling in a vehicle
  • New sidewalks and trails with a boulevard buffer between the road
  • New paths to use when bicycling
  • New turn lanes in key areas

In addition, all Metro Transit buses and bus stops have returned to 66th Street. For details on your bus route, please visit: https://www.metrotransit.org/rider-alerts

Thank you!

From the entire project team, we would like to thank all local businesses, residents and 66th Street users for your patience and cooperation during the entire 66th Street project and for this final construction season!

MORE INFO


ACCELERATED MILL AND OVERLAY PROJECT

The Accelerated 6-year Mill and Overlay Project is now entering its 5th year. In 2019, concrete crews will be repairing curb and gutter and manhole/catch basins in the areas to be milled & overlaid in 2020. The 2019 Mill & Overlay area is in the southwest corner of town, generally south of 70th Street and west of 35W.

MORE INFO


CENTERPOINT ENERGY-NICOLLET AVENUE

CenterPoint Energy’s authorized contractor, Michels Corporation, has installed 100% of the natural gas main for CenterPoint Energy’s “Nicollet Avenue from 67th Street to Old Shakopee Road” belt line project.

CenterPoint Energy would like to say thank you for your patience as they continue to modernize their system to continue to provide reliable natural gas service. They strive to restore streets and grass disturbed by CenterPoint Energy to as close as possible to their original states, and are committed to completing restoration work quickly, and to a high standard in compliance with all laws. Below are the restoration notes

  • Temporary asphalt on sidewalks
    As CenterPoint Energy’s authorized contractor, Michels Corporation, is finishing pipeline work for the 2018 season, crews from Q3 Contracting, CenterPoint Energy’s authorized contractor, are restoring the areas affected by Michels Corporation’s work. As winter is approaching, Q3 Contracting is beginning to lay down temporary restoration for the hard and soft surfaces. In some areas, the crews are replacing previously concrete sidewalk panels with temporary asphalt. These panels will receive permanent concrete in spring or summer 2019.
  • Winter erosion control for lawns
    When temperatures aren’t conducive for planting grass, Q3 Contracting will apply winter erosion control called hydromulch (otherwise known as hydroseed). The crews apply hydromulch by spraying it onto the affected areas. Sometimes the crews place netting with hydromulch to keep the soil together. Hydromulch is safe for pets to touch, but CenterPoint Energy recommends leaving it alone until the crews return in the spring. (See image below.) Permanent soft-surface restoration involves the crews’ placing black dirt and planting grass seed in the affected areas. Any holes created by CenterPoint Energy’s crews in boulevards during construction will be backfilled with dirt and sprayed with hydromulch in cold weather. In spring, Q3 Contracting will return to place black dirt and grass seed in these areas.

MORE INFO


RICHFIELD PARKWAY-CHAMBERLAIN DEVELOPMENT

Construction is in full swing and crews are making fantastic progress on the Chamberlain Development. Richfield Parkway between 66th and Cedar Avenue is now open, except for a temporary 1-month closure of Richfield Parkway south of 66th St.

MORE INFO


77TH STREET UNDERPASS

SCHEDULE:
Design: 2017-2019
Construction: TBD

MORE INFO