To improve the pavement conditions and upgrade the aging storm sewer, santiary sewer and watermain.

69th_StreetThe approximate limits of the project are Knox Avenue to Humboldt Avenue.

PROJECT ELEMENTS

  • Remove Curb and Gutter
  • Remove Asphalt Roadway
  • Replace Storm Sewer, Sanitary Sewer and Watermain
  • New Curb and Gutter and Driveway Aprons
  • Repave Roadway

TIMELINE

April 2015-June 2015

The contractor completed substantial completion in June. Final project work is expected to be complete by August.

PROJECT FINANCING

The 69th Street Storm Sewer Improvement Project is funded by street reconstruction bonds